Client: ISG
Contract Value: £1.5 Million
Duration: 28 Weeks
Information: Piling, drainage, groundworks, RC Frame, all exposed
concrete to ground floor area. Marney Construction were called to a
meeting in Cambridge by ISG Construction to ascertain the feasibility
of completing an abandoned RC frame whereby, the previous
contractor had gone into liquidation. This included the removal of 1.5
floors of false work which was deemed not fit-for-purpose. Under great
pressure, Marney Construction managed to pull this job round for ISG.